OUR GENERATION LIMITED AGAINST ABERDEEN CITY COUNCIL [2018] ScotCS CSOH_124 (21 December 2018)


BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?

No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!



BAILII [Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback]

Scottish Court of Session Decisions


You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> OUR GENERATION LIMITED AGAINST ABERDEEN CITY COUNCIL [2018] ScotCS CSOH_124 (21 December 2018)
URL: http://www.bailii.org/scot/cases/ScotCS/2018/[2018]_CSOH_124.html
Cite as: 2019 GWD 2-27, [2018] ScotCS CSOH_124, 2019 SCLR 482, [2018] CSOH 124

[New search] [Printable PDF version] [Help]


Page 1 ⇓
CA3/18
OUTER HOUSE, COURT OF SESSION
[2018] CSOH 124
OPINION OF LADY WOLFFE
In the cause
OUR GENERATION LIMITED
Pursuer
against
ABERDEEN CITY COUNCIL
Defender
Pursuers’ Counsel: MacColl QC et Turner; Eversheds Sutherland (International) LLP
Defenders Counsel: Mure QC; Morton Fraser
21 December 2018
Introduction
Background
[1]       The pursuer owns and operates roof-mounted photovoltaic systems on buildings
(“the equipment”). The equipment collects solar energy and converts it into electricity,
which the pursuer thereafter sells. The defender, a local authority, owns and operates a
large number of properties in Aberdeen where the equipment is installed. These
arrangements and installations are covered by a Master Agreement (entered into between
Page 2 ⇓
2
the pursuer and defender) and by 72 individual site agreements (entered into among the
pursuer, the defender and a third party “the Mark Group Limited” (hereinafter “the third
party”)) governing the installations of the system on each of the defender’s properties.
[2]       By emails sent on 25 July 2017 (“the email”) and subsequent termination notices the
pursuer endeavoured to terminate each of the site agreements.
[3]       In this action the pursuer seeks declarator that it has validly terminated each of the
site agreements (in conclusion one) and declarator of the defender’s liability to pay the
necessary cost of removing the equipment comprising the systems (in conclusion two). It
also seeks payment of a figure exceeding £8 million (in conclusion three). The defender
challenges the validity of the termination notice relied upon by the pursuer for the purposes
of its first conclusion for declarator. As the pursuer’s other conclusions are dependant on
the validity of the termination notices, if the defender is correct then the pursuer’s whole
action falls.
Issue debated
[4]       At procedure roll debate the defender challenged the validity of the termination
notice relied upon by the pursuer. There was no discreet challenge to the form of the
termination notice itself. Rather, the question was whether the email constituted a “written
notice from the former Party requiring payment” in accordance with clause 8.4.3. The
defender argued that, as a necessary precondition to the service of any termination notice,
the pursuer first required to give written notice requiring payment which complied with
clause 8.4.3 of the site agreement. Before considering parties’ arguments, it is necessary to
set out the relevant contractual provisions in the site agreements and the terms of the email
and termination notice relied upon. It is necessary to refer only to one of each of the site
Page 3 ⇓
3
agreements, emails and termination notices as, apart from relating to the specific properties,
they are otherwise in identical terms.
The contractual provisions in the site agreements
Clause 8: Termination
[5]       Extensive reference was made in the pleadings to provisions in the Master
Agreement and the site agreements. For the purposes of the debate it suffices to note the
terms of clause 8 and, as parties made reference to some other clauses, to summarise these
other clauses (namely, clauses 1.1, 6.1, 6.2, 6.7 to 6.8, 10 and 12 of the site agreement).
Clause 8 is headed “TERMINATION”. Clause 8.1 provides that the site agreement is to
subsist until the 25th anniversary of the commencement date, subject to the remaining
provisions of clause 8. Clauses 8.2 and 8.3 govern removal of the equipment following the
expiry date and enables the defender to offer to purchase the equipment.
Clause 8.4: early termination of the site agreement
[6]       Clause 8.4, which is more detailed, provides the mechanism for early termination of
the site agreement in three circumstances specified in sub-clauses 8.4.1 to 8.4.3. So far as
material it states:
“8.4. Any Party may terminate this agreement with immediate effect upon written
notice to the other Parties if any of the following events shall occur (but subject
always to the terms of any Direct agreement entered into):
8.4.1 if the other Party commits any breach of its material obligations under
this agreement (including the obligations contained in clause 18) and fails to
remedy such breach, if capable of remedy, within 30 days after receiving
written notice form (sic) the other Party requiring it to do so; or
[….]
8.4.3 if the other Party fails to make punctual payment of any amount
properly due to the former Party under this agreement and such amount
Page 4 ⇓
4
remains unpaid at the expiry of 20 Banking Days after receiving written
notice from the former Party requiring payment;” (emphasis added).
The pursuer relies on clause 8.4.3 to terminate the site agreements. The parties differed as to
whether the email complied with the words in bold in clause 8.4.3. (An argument about an
alleged want of proper service of the written notice was not insisted in.) Clause 8.5 provides
for the pursuer’s right to terminate in other circumstances which are not here relevant.
Clause 8.7 requires the defender to pay the pursuer a sum calculated by reference to
schedule part 3 of the site agreement in the event the termination arises as a result of the
“default” of the defender under inter alia clause 8.4.3.
The other clauses of the site agreements referred to: 1.1, 6.1, 6.2, 6.7 to 6.8, 10 and 12
[7]       Passing reference was made in the course of the debate to several other provisions, as
follows:
1.1 “Party” means Mark Group, the Council or Our Generation and, together, the
Parties.
6.1 Mark Group (on behalf of Our Generation [ie the pursuer]) will issue an
electronic invoice for the Metered Output once a month and the Council [ie
the defender] shall pay the Charges set out in each invoice within 20 days of
its receipt. […]
6.2 If in respect of any invoice referred to in clause 6.1, a Party ascertains that
information used in preparation of such an invoice is subsequently altered,
the Party shall within 14 days of so ascertaining such alteration issue a
statement showing the difference between the Charges paid or payable in
accordance with such statement and the Charges which would have been so
Page 5 ⇓
5
payable if such statement had been prepared on the basis of the altered
information. Statements will be submitted with an invoice for the revised
amount due, or by agreement of the Parties the reconciliation shall be carried
out at the time the next Monthly or other statement is submitted and included
in the invoice issued in respect of it.
6.7 If any statement or invoice submitted in accordance with clauses 6.1 or 6.2 is
disputed or subject to question by either Party: […]
6.8 In the event that Our Generation changes its collection agent it shall give at
least 10 Banking Days prior written notice to the Council.
The site agreement also contained an entitlement of the pursuer to assign its rights and
obligations to a subsidiary or holding company (clause 10.2) or to transfer its rights and
obligations under the site agreement and its title to the equipment (clause 10.3). Reference
was also made to clause 12, containing the provision for “NOTICES”. Clause 12.1 stipulated
that “Any notice given by either Party to this agreement shall be in writing and shall be
deemed duly served if delivered personally or sent by facsimile transmission or by prepaid
registered post to” specified addresses and fax numbers. There are also more detailed
deeming provisions about the timing of receipt, but these are not relevant to the issue
debated. (An argument about a want of proper service was not insisted in.)
The documentation the pursuer relied upon to effect termination
The email relied on as constituting the written notice under clause 8.4.3
[8]       It was common ground between the parties that the pursuer required to give written
notice complying with clause 8.4.3 before it could exercise the right to terminate under
clause 8.4. The pursuer relies on the email sent by a named individual of “Effective Energy
Page 6 ⇓
6
dated 25 July 2017 to a named individual of the defender. The subject given for the email
was “Statement of Account”. Apart from a brief salutation and sign off, the whole text of the
email stated: “Please see attached statement of balances now overdue, owing to Our
Generation Solar.”
The statement attached to the email
[9]       The document attached to the email (“the statement”) took the form of a summary
statement. This bore to be issued in the name of “Our Generation Solar 2 Ltd” at an address
in East Sussex (at the top left of the statement). Otherwise at the top right the statement
contained a logo (the letter “G” in blue contained within the red letter “O”) above the words
“Our Generation” and, in much smaller font immediately below that, the phrase
Generating Renewable Energy together” (“the OG logo and strapline”). The statement is
addressed to a named individual within the defender. The body of the statement contains
12 lines of entry with seven columns. It suffices to note that each line contains the same date
as the statement (i.e. 25 July 2017); each was said to be due six days earlier and the invoice
figures on each line range between £1,200 and £67,000. At the foot of the page there is a
further box, typically found on statements of account, recording sums said to be due within
the “current” period, period 1, period 2 and so on. The total of £216,399.24 is recorded as
falling within “period 1”and that same figure appears in boxes at the foot of the page
marked “Invoice Value Overdue” and “Total Amount Due”.
The invoices supporting the statement
[10]       Reference was made to a sample invoice dated 19 June 2017 relative to the entry on
the statement for £57,155.11 (at 6/9/1 of process). This invoice was addressed to a named
Page 7 ⇓
7
individual within the defender’s Council Offices. It contained the OG logo and strapline at
the top right. The narrative referred to solar photovoltaic services” and stated that “OGS2
Lost Revenue Due to ACC Insurance Position (Apr 15-Mar 17 Inclusive)”. The “Terms”
were stated to be “net monthly account” and the payee details at the foot of the page
correctly stated the name of the pursuer but provided the wrong company number.
Parties’ comments on the terms of the email and on inaccuracies in the statement and
invoice
[11]       The defender highlights a number of errors or discrepancies in the email, statement
and accompanying invoices, as follows:
(1) the email had not been served on the third party to the site agreement, namely
the Mark Group Ltd;
(2) the sender of the email, “Effective Energy”, was not a known agent of the
pursuer;
(3) nowhere did the email provide the pursuer’s own company name.
The defender also notes that the invoices were recorded as only 6 days overdue. The
pursuer’s reply is that “Our Generation Solar” is the trading name of the pursuer and the
corporate group to which it belonged.
[12]       In relation to the statement itself, the defender notes that a company known as “Our
Generation Solar 2 Ltd” is not a party to either the Master Agreement or any of the site
agreements. Again, the pursuer is nowhere referred to in the statement. While it was
acknowledged that the pursuer could assign its rights under the site agreement, this had not
happened as no intimation of any assignation had ever been given to the defender. The
pursuer did not rely on any assignation. The pursuer points out that the statement contains
Page 8 ⇓
8
the correct OG logo for the pursuer itself. In relation to the sample invoice, this bears in the
narrative to relate to a different company (“OGS2”). The pursuer again notes that the OG
logo and strap line are those of the pursuer and its corporate group and the pursuer is
correctly referred to as the payee. It was accepted that the wrong company number was
provided.
The termination notice
[13]       The pursuer’s agents sent a letter dated 24 August 2017 to the defender’ offices (“the
termination notice”). The Termination Notice subject headings referred to the pursuer and
stated “Termination Notice in respect of” a specific site agreement at one of the properties.
After referring to the pursuer and the site agreement in respect of the particular property,
the termination notice narrated that the defender had “failed to make punctual payment in
respect of invoices properly due under” the site agreement; that this sum due had remained
unpaid at the expiry of 20 Banking days following the defender’s receipt of the email. The
termination notice thereafter provided that, pursuant to clause 8.4.3 of the site agreement, it
was terminated with “immediate effect”. There followed a demand following the
termination of that particular site agreement.
The law
[14]       It was common ground between the parties that the law applicable to the validity of
a notice served in terms of a contract had recently (and for this court, authoritatively) been
discussed by the Second Division in HOE International Ltd v Andersen 2017 SC 313, in which
Lord Drummond Young delivered the Opinion of the Court. The relevant legal
propositions vouched by the case law include the following:
Page 9 ⇓
9
(1) Where the validity and effect of a notice provided under a contract is in issue,
two distinct types of question may arise. First, are the terms of the notice
sufficient to convey the necessary information to the recipient (“the first HOE
question”)? And second, has the notice been issued in accordance with the
contractual provisions governing the notice procedure (“the second HOE
question”)? (See HOE International Ltd at paras 16 & 28). I shall refer to these
collectively as the “HOE questions”.
(2) The first HOE question turns largely on the construction of the notice itself. This
exercise falls to be carried out in accordance with the ordinary principles of
contractual construction. The construction of the notice must be approached
objectively, the issue being how a reasonable recipient would have understood
the notices, taking into account the relevant objective factual context. The
subjective knowledge or awareness of the actual recipient is not therefore
relevant: see HOE International Ltd at paragraphs 28 and 31; Mannai Investment Co
Ltd v Eagle Star Life Assurance Co Ltd [1997] AC 749 per Lord Steyn at pp767D-
769B, Lord Hoffmann at p775B-C and Lord Clyde at p782D-E.
(3) The purpose of a contractual notice is important, as is the purpose of any
particular requirement that has not been complied with (HOE International Ltd at
paras 29, 34 and 53).
(4) A notice must be sufficiently clear and unambiguous to leave a reasonable
recipient in no reasonable doubt as to how and when it is intended to operate;
though absolute absence of any ambiguity is not necessary: see Mannai Investment
Co Ltd (sup cit.) at p782B-D per Lord Clyde. The correct test is: “Is the notice
quite clear to a reasonable tenant reading it? Is it plain that he cannot be misled
Page 10 ⇓
10
by it?” (see Carradine Properties Ltd v Aslam [1976] 1 WLR 442 per Goulding J at
p444, adopted by the House of Lords in Mannai Investment Co Ltd and cited by
Lord Reed in Credential Bath Street Ltd v Venture Investment Placement Ltd 2008
Hous LR 8 at para 46).
(5) As for contractual requirements for a valid notice (the subject matter of the
second HOE question), the crucial question is whether strict compliance is
required with one or more requirements of the clause that empowers the sending
of a notice; a question to which the ordinary principles for the construction of
contracts are applicable. The more drastic the consequences of the notice, the
greater the need for strict compliance (HOE International Ltd at paras 32-34, 40).
(6) Where strict compliance is required by the contract, then any failure to comply
with the contractually agreed requirements will render the notice invalid: see
West Dunbartonshire Council v William Thompson & Son (Dumbarton) Ltd
2016 Hous LR 8 (Ex Div) per Lord Menzies (delivering the Opinion of the Court) at
para 31; Mannai Investment Co Ltd (sup cit.) at p776B per Lord Hoffmann. Thus,
in respect of the second type of question (see para 13(1), above), the test in
Mannai Investment Co Ltd is not relevant.
The parties’ submissions
The submissions on behalf of the defender
[15]       Mr Mure QC, who appeared on behalf of the defender, made clear that its debate
proceeded on certain hypotheses (but not otherwise conceded). The hypotheses were
(1) that the sum set out in the invoices were “properly due” in terms of clause 8.4.3;
Page 11 ⇓
11
(2) that at the time of the termination notices issued on behalf of the pursuer it was
not itself in breach of contract such as to disentitle it from invoking the
termination procedure; and
(3) that the termination notice had also been served upon the Mark Group Ltd.
Accordingly, the narrow issue between the parties at debate is whether the email together
with the accompanying statement and supporting invoices constituted “written notice from
the former Party requiring payment”.
The second HOE question
[16]       Mr Mure QC argued that in all the circumstances, the email and its attachments did
not constitute a “written notice from the former Party requiring payment” in terms of
clause 8.4.3, and the termination notices did not validly terminate the site agreements. In
order for the termination notices to be valid under clause 8.4, it is necessary that in respect of
each site agreement a written notice satisfying the requirements of clause 8.4.3 is first served
by the pursuer on the defender and on Mark Group Ltd.
[17]       He argued that a clause such as 8.4.3 served several purposes, namely:
(i)
to empower the pursuer to terminate each site agreement with immediate
effect if any amount properly due and identified in the notice in respect of
that site agreement remains unpaid at the expiry of 20 Banking Days after
service of the notice;
(ii)
to put the recipient of the notice on warning that in order to enable that
power to be used the other party is requiring payment of an identified
amount remaining properly due in respect of that site agreement, that
being the amount to be paid if the recipient is to prevent the pursuer from
Page 12 ⇓
12
obtaining the power to terminate the site agreement with immediate
effect; and
(iii)
to specify in respect of the particular site agreement to which the notice
relates, the amount that the pursuer requires the defender to pay.
The notice’s function is therefore to notify information to the recipient in accordance with
the contractual requirement, on which that recipient can then act to protect or vindicate its
rights.
[18]       It is not the existence of overdue invoices but the recipient’s failure to comply with
the requirement in a valid clause 8.4.3 written notice which provides the basis for the
pursuer to terminate the site agreements. The consequence of a valid termination notice is
drastic, bringing the parties’ contract to an end, potentially long before its intended expiry
25 years from the Commencement Date: see clause 8.1. The termination provisions in clause
8.4 are key terms of the parties’ site agreements. Strict compliance with clause 8.4.3 is
therefore required.
[19]       I did not understand Mr Mure QC to insist on his submission that there had not been
due “service” of the written notice (ie the email and supporting documentation). Otherwise,
he argued in relation to the formality of the “notice” that the concept of a “written notice” in
the site agreements imports an element of formality commensurate with the seriousness of
the consequences that may follow. He noted that the site agreement deals with invoices and
statements in terms, in other provisions: see e.g. clause 6.1, 6.2 and 6.7. A notice is not
therefore to be equiparated with an invoice or statement.
[20]       Turning to the email, this stated that it attached a “statement of balances now
overdue”. The attached document was headed “Statement” and included the reference to
individual invoices (I have described this above, at paras [8] to [10]). Invoices and
Page 13 ⇓
13
statements may be expected to indicate what sums one party asserts are due in terms of each
particular site agreement. However, he submitted that such documents are not equivalent
to written notices requiring payment of particular sums in respect of particular site
agreements. The email and attachment are not, therefore, formally valid as notices under
clause 8.4.3 such as to empower the pursuer thereafter to issue a termination notice in
respect of any or all of the site agreements.
The first HOE question
[21]       As a fall back he argued that, contrary to the above submission strict compliance is
not required and/or the email and attachment are to be regarded as constituting a “written
notice”, they are nonetheless invalid on the basis that the reasonable recipient would be left
in no doubt about the pursuer’s intention. In other words, the terms of the email and
attachment do not convey to the reasonable recipient the meaning required by the purposes
which the parties have agreed the provision in clause 8.4.3 should serve. In particular,
(1) The email and attachment did not intimate anything beyond the fact that
invoices have been issued and are overdue. Re-statement of that fact does not
constitute a notice “requiring payment”.
(2) The email and attachment did not mention clause 8.4.3 of any site agreement.
(3) The statement attached to the email was not a written notice bearing to be
issued by or on behalf of the pursuer. It was a statement from a separate
company, Our Generation Solar 2 Ltd with an address in Hove. That name
matches the company number listed on the invoices. The defender owed no
obligation to that company under either the Master Agreement or the site
Page 14 ⇓
14
agreements. Neither the email nor the statement makes reference to the
pursuer.
(4) Given (i) the contractual provisions anent assignation and transfer, (ii) the use
in the email and statement of a company and number different from the
pursuer’s, and (iii) the fact that the email was issued by a party other than the
Mark Group Ltd (cp clause 6.8), even if the email and statement could be
construed as “requiring payment” and thus evincing an intention to create the
power provided for in clause 8.4 (which is denied), the reasonable recipient
would be in doubt about the proper payee.
(5) The invoices referred to in the statement dated 25 July 2017, although dated 16
and 19 June 2017, bear to include sums being charged in relation to periods
from April 2015 to 31 May 2017. Standing the dates of such invoices, and the
periods to which they and their attendant breakdowns refer, the email and
statement do not convey the impression that the pursuer intends to exercise
any rights it may have had under clause 8.4.3 to terminate any site agreement
with immediate effect.
(6) Clause 8.4.3 requires service of a written notice under the individual site
agreement, concerning amounts properly due under that site agreement. The
email and attachment mention no specific premises nor any specific site
agreement under which notice was being served.
(7) Clause 12 of each site agreement provides for notices to be in writing and to be
served upon the addressees or facsimile numbers of each of the three parties to
the site agreements. The email and attached statement were not served upon
Page 15 ⇓
15
Mark Group Ltd; nor were they served personally, by facsimile transmission or
by prepaid registered post.
(8) In these circumstances, even if the procedure was formally valid, a reasonable
recipient of the email and attached statement would not have understood those
documents as (i) being more than a statement of account or (ii) intended to
form the basis for service of a notice of termination by the pursuer under clause
8.4.3; or at least would have been in doubt about the contractual position.
(9) The circumstances founded upon above are not mere technical matters, but are,
both individually and in combination, essential matters going to the pursuer’s
jurisdiction or power to issue a notice terminating the various site agreements
with immediate effect.
(10) The reasonable recipient would have been aware that certain invoices had
become overdue; but would not have been aware from the email and
attachment that payment in respect of each site agreement was now being
“required” so as to trigger the pursuer’s power to terminate each agreement
with immediate effect.
[22]       In construing the parties’ contract, and the purported notice, a commercially sensible
construction points to the need for strict compliance, and in favour of the defender’s
position. Commercial people understand the basic distinction between an invoice or
statement, and a formal written notice requiring payment and intended to trigger a right to
terminate a long term contract. Commercial people would not understand the mere
repetition of an invoice previously issued as importing a special requirement to pay in terms
of clause 8.4.3. Given the structure of the parties’ contracts, the potential consequences in
terms of termination, the circumstances above, and the prejudice to the defender of failing to
Page 16 ⇓
16
give formal notice requiring payment (thus putting the defender on notice that clause 8.4.3
was in play), a commercially sensible construction does not support the pursuer’s position.
[23]       Accordingly, even if the three hypotheses he identified (see para [16], above) were to
be the subject of proof and were resolved in the pursuer’s favour, the pursuer would have
failed validly to terminate the site agreements. The Court should sustain the defender’s first
plea in law and dismiss the action.
Submissions on behalf of the pursuers
Motion
[24]       Mr MacColl QC, who appeared on behalf of the pursuer, explained that his primary
position was that the relevancy of the pursuer’s case can only be determined after proof and
he invited the Court to refuse in hoc statu the defender’s motion to sustain its first plea-in-
law. He moved the Court to allow a proof before answer on all issues. He sought a proof of
8 days.
Outline of pursuers position
[25]       In relation to the documentation, the pursuer accepts that there are minor errors
(some details belonging to a related company) within the terms of the statements that
accompanied the email and the invoices to which it refers. However, there were no errors
within the terms of the emails (which Mr MacColl QC referred to as “Default Notices”)
themselves. The parties had been dealing with the project for several years; there was no
ambiguity as to the co-parties to the contract or the obligations owed thereby. A reasonable
recipient would have construed that the invoices were issued on behalf of the pursuer. In
the circumstances, a reasonable recipient in the position of the defender would have
Page 17 ⇓
17
understood the terms and effect of the emails and the termination notices. On a proper
construction they were effective to terminate the site agreements. Mr MacColl QC referred to
clauses 6.1 and 8.4.3 of the site agreements. It is was the pursuer’s case that these provisions
were followed. In particular, the pursuer issued invoices to the defender; it gave notice
constituted by email pursuant to clause 8.4.3 requiring payment of sums overdue in terms of
the invoices as set out in a statement of account attached thereto; and it thereafter
terminated the site agreements by written notices constituted by termination notices.
Interpretation of the documentation: the first HOE question
[26]       Mr MacColl QC argued that the relevant context for the interpretation of the email
was comprised of the invoices and statements. In relation to the invoices, Mr MacColl QC
submitted that the invoices form a major constituent of the context within which the
contractual notices must be interpreted. The invoices were issued under the terms of the site
agreements. The pursuer offers to prove as much. Subject to questions surrounding the
rates applicable, the invoices have been paid by the defender. Invoices had been paid for 4
years. The invoices were issued in the name of the pursuer. They contained the pursuer’s
VAT number. For reasons unknown, they have been issued with the wrong company
number - for a company related to the pursuer. However, as the defender observes, it is
only the pursuer that is party to the site agreements. There was no assignation or transfer of
rights to Our Generation Solar 2 Limited. That was known by the defender and a
reasonable recipient in the position of the defender would have understood that any
references to Our Generation Solar 2 Limited’s details must accordingly be erroneous. He
submitted that on any reasonable view, the invoices bear to have been issued by the pursuer.
Page 18 ⇓
18
There is no possible ambiguity and any reasonable observer would have known that these
invoices related to the site agreements. Indeed, the defender itself has so proceeded.
Invoices to be issued/disputed
[27]       Under reference to certain other provisions of the site agreement, Mr MacColl QC
submitted further that the defender is deemed to know that in terms of the site agreements
monthly invoices were to be issued (clause 6.1). If the defender disputed any invoice, it was
required to pay the undisputed and unquestioned items (clause 6.7.1) and otherwise set out
its reasons for disputing or questioning the amounts in writing (clause 6.7.2). The invoices
were not disputed. The site agreements provide for this position to be remedied in terms of
a clause 8.4.3 default notice. As a provision of the site agreements, the defender is deemed
to be aware of that consequence. It is in this context that the email was given.
The email
[28]       Mr MacColl QC noted that the email referred to the trading name of the pursuer
rather than its company name. No issue is taken with the addressee, who was an employee
of the defender dealing with the site agreements. He submitted that a reasonable recipient
in the position of the defender (or its employee) would have known that this was being sent
on behalf of the pursuer. Even if that were not the case, the correspondence was sent by the
pursuer’s collecting agent, Effective Energy. The pursuer was entitled to appoint Effective
Energy as its collecting agent (clause 6.8 of the Site Agreement). The pursuer offers to prove
that Effective Energy had been so appointed and the defender informed timeously to the
issue of the email. In that context, a reasonable recipient would have construed that
Effective Energy were referring to the pursuer and dispatching a notice on their behalf. On a
Page 19 ⇓
19
plain reading, the purpose of the email was to inform the defender that the invoices referred
in the statement attached thereto were overdue.
The statement
[29]       Turning to the statement Mr MacColl QC noted that it contained the pursuer’s logo.
It referred to a number of invoices by reference to their individual dates, invoice references
and amounts. He accepted that the statement bears to have been issued erroneously with
the name of “Our Generation Solar 2 Limited. However, for the reasons he had already
submitted, there can be no reasonable doubt that the invoices referred therein were those
issued by the pursuer and falling due in terms of the site agreements to the pursuer.
[30]       In the circumstances, any reasonable recipient with the knowledge of the fact of the
site agreements between these parties; the installation of the PV Equipment; the Energy
production therefrom; the overdue invoices; that payment remained outstanding; and that
this was due to the pursuer, would have construed the statement and hence the email to
refer to the obligations in respect of which the defender was in default.
The second HOE question
[31]       In relation to the second of the HOE questions, Mr MacColl QC argued that
clause 8.4.3 does not require any particular form, merely that the notice be in writing. On an
ordinary construction, email is a form of writing. At times, the defender appeared to
suggest that a statement with a request for payment would not constitute a notice under
8.4.3. It appeared to do so under reference to clauses 6.2 and 6.7 and an extrapolation that a
“statement” is a specific form of document under the site agreements. All contractual
references to “statements” within clauses 6.1, 6.2, 6.3 and 6.7 relate to statements of account
Page 20 ⇓
20
for sums which are not overdue. However, there is nothing within the terms of those
clauses to suggest that this is in the only purpose to which a statement might be used.
Indeed, Mr MacColl QC argued it is commercially nonsensical to suggest that a statement
could not be issued to set out the sums which the defender is required to pay in satisfaction
of a notice under clause 8.4.3. Provided the terms of the notice accompanying that
communicated that payment was required, that is all that is formally necessary.
The terms of the site agreement
[32]       Mr MacColl QC noted that there is no provision within the terms of the site
agreements for the pursuer to provide details of the sums due other than in respect of sums
which have not yet fallen due as a result of an invoice (clause 6.1), a statement following
alteration of an invoice (clause 6.2), a statement following reconciliation (clause 6.3), or sums
requiring payment as overdue (clause 8.4.3). He submitted that the email (whether
accompanied by a statement or not), being expressly in respect of overdue sums, was not a
statement under clause 6.2 or 6.3. It was not an invoice under clause 6.1. It stated in plain
terms that the amounts referred in the statement were overdue. On a proper construction,
the term “overdue” to a reasonable recipient dictates and stipulates that immediate payment
is required. That is all that is required to satisfy the terms of clause 8.4.3. Accordingly, the
email satisfies the requirements of clause 8.4.3 and was valid.
Intention to create a power
[33]       In relation to the defender ‘s suggestion that notice of an intention to “create a
power” is required, Mr MacColl QC submitted that no such requirement can be gleaned
from a proper construction of clause 8.4.3. The reasonable co-party recipient is deemed to be
Page 21 ⇓
21
aware of the terms of the contract (HOE International Limited at para 29). There is no reason,
therefore, for such notice to be required. Moreover, no such notice requirements are
provided in respect of other termination rights: as, for example, clause 8.5. It is not clear
why, in this context, a more onerous interpretation should be afforded to clause 8.4.3 to
protect the defender from consequences of which it is deemed to be aware.
[34]       Mr MacColl QC argued that it is not clear whether the defender seeks to take issue
with the notice being served by an agent. There is nothing within the terms of the site
agreement to suggest that agents cannot effect notices. It has no bearing on the reasonable
recipient’s understanding beyond the issues previously addressed. This is not an additional
formal requirement. If this criticism is directed at the lack of a written notice more generally,
that is constituted by the email.
[35]       The email was:
(1) served by the pursuer’s duly appointed collecting agent;
(2) on behalf of a principal identified by their trading name;
(3) in respect of whom there was no ambiguity in the full context of the parties’
dealings;
(4) with reference to invoices patently referring to the sums due under the site
agreements;
(5) in respect of sums that were overdue and required immediate payment; and
(6) to a party who is deemed to be fully aware of its contractual obligations.
In that context it would have been construed by a reasonable recipient as a notice for the
purposes of clause 8.4.3.
Page 22 ⇓
22
The termination notice
[36]       Mr McCall noted that no distinct argument was addressed to the termination notice.
On a proper construction, it met the formal requirements of clause 8.4 to be in writing. For
the purposes of this debate, it is accepted that the sums were due and that the pursuer was
not in breach. The termination notices were accordingly effective to terminate the site
agreements. Accordingly, the pursuer should be allowed a proof of its averments.
Discussion
The second of the HOE questions: the compliance of the email with clause 8.4.3
[37]       As noted in the case of HOE International Limited (at para 16, see para [14(1)], above),
two questions generally arise in cases concerning the validity and effect of a notice provided
under a contract. It is convenient to begin with the second question, namely, whether the
written notice comprising the email complied with clause 8.4.3.
The guidance in HOE International Limited
[38]       The Inner House in HOE International Limited affirmed that this is a question of
contractual interpretation applying the ordinary principles of the construction of contracts.
The crucial question was whether the relevant contractual provision required strict
compliance with one or more of the requirements empowering the sending of a notice. The
court emphasised three additional matters: first, that, in this context, a purposive
construction was particularly important; further, that the more drastic the consequence of a
notice the greater the need for strict compliance; and finally, that in the absence of prejudice
to the recipient party the court should be slow to hold that failure was fatal to the validity of
the notice. (See paras 17, and 32 to 36 of HOE International Limited.)
Page 23 ⇓
23
What does clause 8.4.3 require?
[39]       It was common ground between the parties that clause 8.4.1 empowered a party to
terminate the site agreement in certain circumstances. The particular circumstance the
pursuer relied on for the purpose of clause 8.4.3 was the asserted failure of the defender to
make punctual payment of amounts due to the pursuer. It was accepted by both parties, in
my view correctly, that the giving of the appropriate written notice under clause 8.4.3 was a
necessary precondition to the subsequent service of any termination notice by the party
wishing to terminate.
[40]       The giving of the written notice operated as a “trigger” putting the defender on
notice that the pursuer wished to exercise the power to bring about an early termination of
the site agreement. Whether the pursuer could permissibly exercise that right of immediate
termination depended on whether the amount properly due remained unpaid after the
expiry of 20 Banking Days after the defender had received written notice from [the
pursuer] requiring payment” (emphasis added). In my view, this is an important
qualification of the exercise of the power to terminate in two respects. First, it was clearly
intended to give the party against whom the power of termination might potentially be
exercised the right to take certain steps, if it chose, to preclude the exercise of that power.
That took the form of being afforded a period of some four weeks to pay the amounts
properly due (or, arguably, to dispute whether some or all of the sums claimed were
“properly due”- though that issue is presumed for the purpose of the debate). This is a
significant countervailing right to what is undoubtedly a drastic consequence flowing from
the exercise of the power to terminate and the issue of the termination notice. Secondly,
and related to the first observation, the simple fact that sums are unpaid is not what entitles
Page 24 ⇓
24
the pursuer to exercise the right of termination. It is the defender’s subsequent failure to pay
the unpaid amount within 20 Banking Days required of it by the written notice. The effect of
this part of clause 8.4.3 is to change the character of an overdue balance (which is a neutral
factor in and of itself and which parties may or may not have tolerated in their dealings),
into a form of default (ie unpaid for 20 Banking Days after receipt of the notice requiring
payment). Mr MacColl QC appeared to accept this, as he consistently referred to the email as
a “Default Notice”. If all that was required was a sum that was overdue, then clause 8.4.3
would be otiose. The requirement that there be a “default” (not just an unpaid sum) is in my
view wholly consistent with the drastic consequence flowing from exercise of the
contractual power to bring about immediate termination. There could hardly be a more
drastic consequence than immediate termination. Accordingly, this invites stricter
compliance with the terms of clause 8.4.3. Further, in my view, on a proper interpretation of
clause 8.4.3 (and following the approach enjoined in HOE International Limited) clause 8.4.3
has a dual quality. First, the factual circumstance stipulated in clause 8.4.3 as the
precondition for the exercise of the right in clause 8.4 (to effect immediate termination) is the
occurrence of the default. The party seeking to exercise that power must send a written
notice capable of bringing about that default. In other words, the sums due (even if overdue)
must be converted into a default. A simple statement of fact that the sums are due or
overdue will not suffice; payment must be required. Secondly, in order to comply, the
written notice must also communicate to the other party that the pursuer is requiring
payment and doing so to establish a default (ie to bring about the circumstance stipulated in
clause 8.4.3). This could be communicated in a variety of ways. While it is correct that, as
Mr MacColl QC argued, parties are presumed to know the terms of the site agreement, one
of the functions of clause 8.4.3 is to give the other party notice that a potential default is
Page 25 ⇓
25
being triggered and to afford it the contractually stipulated standstill period within which it
may remedy that default.
[41]       The terms of clause 8.4.1 (quoted above, at para [5]) reinforce this analysis. Of the
two other circumstances entitling the exercise of the power under clause 8.4 to terminate,
clause 8.4.1 is analogous to clause 8.4.3. (Clause 8.4.2 is not analogous, because it concerns
events brought about by the actions of the third parties.) In clause 8.4.1 a similar
mechanism is deployed: one party may serve a written notice to the other informing it of a
material breach; the other party is allowed a period of time within which to remedy that
material breach; which failing, the party who sent that notice can terminate the site
agreement with immediate effect. Again, being in material beach does not suffice: it is the
creation of the default by sending a written notice of material breach coupled with the other
party’s failure to purge that default, which enables the sender of the notice to exercise the
power of immediate termination.
[42]       Properly construed, as a minimum clause 8.4.3 required a “written notice from the
former Party requiring payment. Did the email (read with the supporting documentation)
comply? I turn to address that question.
Did the email comply with clause 8.4.3?
[43]       While there might be arguments arising under this clause about whether sums were
“properly due” or whether the defender failed to make punctual payment, the factual
hypotheses on which the debate proceeded (see para [16], above) preclude such arguments.
[44]       It is relevant to note that the site agreement was anticipated to operate for 25 years.
Absent early termination, therefore, it would subsist until April 2037. The pursuer sought to
exercise the right of immediate termination just over five years into that 25 year period.
Page 26 ⇓
26
That potentially drastic consequence of operating the clause 8.4 termination provision brings
in its train a need for stricter compliance with the requirement to give “written
notice…requiring payment”. This does not mean that the communication sent required to
be headed up “notice” or “notice for the purposes of clause 8.4.3or something similar. The
defender did not argue for this. On the other hand, the fact that the email was neither a
“statement” nor an “invoice” (as defined under the site agreement) did not mean that it
necessarily was of the character of a notice”, as the pursuer’s counsel appeared to suggest.
The fact that the clause 8.4.3 is not prescriptive of the form of the notice (so long as it is
written) does not relieve the pursuer of complying with what clause 8.4.3 requires.
[45]       The simple but fundamental question is, did the email “require payment” to the
pursuer such as to create a potential default for the purposes of clause 8.4.3? In my view that
email, even read together with the accompany statement and the supporting invoices, did
not do so. Having regard to the draconian consequence of a termination notice, in my view,
the pursuer required to communicate to the defender its intention to bring about the
circumstances provided for in clause 8.4.3 for the purposes of exercising the right of
immediate termination in clause 8.4. A notice compliant with clause 8.4.3 required to be in
these terms in order to convert unpaid sums into a default (the first function of the clause
8.4.3 notice). It had to require payment for that purpose. However, the text of the email is
almost precatory in its terms: “Please see the attached statement of balances now overdue,
owing to Our Generation Solar.” In my view, a simple statement that the balances were
“overdue” (by 6 days) and “owed” to Our Generation Solar does not fulfil the requirement
of a default notice “requiring payment”. Even if “Our Generation Solar” is understood as
encompassing the pursuer, the written notice for the purpose of bringing about the
circumstance in clause 8.4.3 required, in my view, to make it clear in some manner that
Page 27 ⇓
27
non-payment within the required period would have particular consequences, ie the
pursuer’s exercise of its contractual rights to effect immediate termination. The written
notice requiring payment required to communicate that the “default” circumstance (ie if
sums remained unpaid after 20 Banking Days) was going to be relied upon. This was
essential, not least to ensure that the defender could consider whether to purge that
prospective default and to afford the defender the contractually stipulated period (of 20
Banking Days) to do so. The email (and its supporting documentation) did not
communicate this. It did not comply with the requirements of clause 8.4.3.
[46]       I did not understand Mr MacColl QC to contradict Mr Mure QC ’s submission that
the clause 8.4.3 also required written notice to be sent to the third party and that the pursuer
failed to do so. On the other hand, I did not understand Mr Mure QC to suggest that there
was any prejudice. I would not have been persuaded that this factor, taken on its own,
would have rendered the email (had it otherwise complied) non-compliant. Had the email
otherwise complied, I would have allowed the pursuer a proof on its averments that the
notice had been sent on its behalf by an agent, and that that agent was Effective Energy.
[47]       It follows that the termination notice (accepted itself to be sufficient in terms) was
nonetheless not preceded, as it required to be, by a written notice requiring payment that
complied with clause 8.4.3 . It is therefore invalid. As a consequence, the pursuer has no
relevant basis to contend that it has brought about the termination of the site agreements.
As the remainder of its conclusions are dependent upon the validity of the termination
notice, the action falls to be dismissed.
Page 28 ⇓
28
The first of the HOE questions
[48]       In light of my answer to the second HOE question, it is not necessary to determine
this question. However, on that matter, had it been necessary to determine it, I accept the
defender’s submissions. In particular, I accept all of the points Mr Mure QC made (and
which are recorded in para [21], above). Of these I found points (1), (5) and (8) the most
compelling. The terms of the email, read together with the accompanying statement and
supporting invoices, construed objectively and taking into account the knowledge of the
parties, did not convey (much less unambiguously convey) to the recipient that the pursuer
was “requiring payment” in the sense of bringing into existence the circumstances stipulated
for in clause 8.4.3. In my view, the reasonable recipient of the email with all of the
background knowledge that was reasonably available to the parties, would not have
understood the email (and its supporting documentation) as doing any more than stating
that sums were claimed; that these were overdue by 6 days (even though some bore to be
calculated by, or accumulated with reference to, a time-frame of up to two years preceding
the relative invoice); and (on a generous reading of “Our Generation Solar”) owed to the
pursuer. The reasonable recipient would not have understood the email (and supporting
documentation) as communicating the pursuer’s intention to treat those unpaid sums as
constituting a default and which, if unpaid after 20 Banking Days, such as to entitle it to
terminate the site agreement with immediate effect. Accordingly, I would have upheld the
defender’s challenge and answered the first HOE question in favour of the defender.
Decision
[49]       For the foregoing reasons, I accede to the defender’s motion and will dismiss the
action. I will reserve meantime all question of expenses.